Final shingle border work around mechanical wells July 16th, 2026
Punchlist Items week of July – August, 2026
HVAC / Mechanical Well Construction Schedule Start Date (Last Updated 7/8/2026 at 9:45)
Monday July 6th – Removal of units from buildings 1,2, and 3 – Completed
Tuesday July 7th – Reset of units on buildings 1,2, and 3 – Completed
Wednesday July 8th – Removal of units from – Completed
building 4 – 2 units (2455 1/2, 2457, 2457 1/2 Theresea) – Completed
building 6 – all units – Completed
building 7 – 2 units (2473, 2473 1/2 Theresea) – Completed
building 9 – 4 units (2468, 2468 1/2, 2470, 2470 1/2 Theresea) – Completed
Thursday July 9th – Reset of all units listed above – Completed
Monday July 13th – 15th – Removal & Reset of remaining roof top units
building 5 – 2 units (2463 1/2, 2465 1/2 Theresesa) – Completed
building 8 – 3 units (2462 1/2, 2464, 2464 1/2 Theresea) – Completed
building 10 – 4 units (2464, 2468, 2468 1/2, 2470 Brookwillow) – Completed
building 11 – 2 units (2460 1/2, 2462 Brookwillow) – Completed
building 12 – 3 units (2452 1/2, 2454, 2456 Brookwillow) – Completed
***Note: This schedule could change due to weather or any unforeseen delays***
COPPERSMITH PLUMBING WILL BE RECONNECTING THE GAS LINES TO ALL RTUs THAT WERE A PART OF THIS PROJECT THE FIRST OR SECOND WEEK OF AUGUST, 2026.

Mechanical Wells
Preferred Filing 1 Townhouse EPDM reroofing material.
The mechanical wells have historically been prone to leaking.
Homeowners Association – CAU Insurance


HANG OUT AT THE CLUBHOUSE
During the roofing project the community clubhouse is a great place to hang out.
Stay cool, don’t have to listen to hammers and work crews walking on your roof all day.
Playgrounds and televisions for the kiddos, kitchen to prepare snacks or keep beverages cool in the refrigerator, work out or exercise.

Humpty Dumpsters – Container Locations During Reroofing.
Containers can be expected to be in location for up to 2 days.
Homeowners please inform your tenants of the temporary disruption to parking in the driveways during construction.
Overflow parking in available on: Theresea Lane Parking Area #3, Brookwillow Loop, Brookwillow Loop Parking Area #4, Abas Drive Northside (F3/4 Road)
See HOA Website : Community Parking
TRASH CONTAINER LOCATION / SCHEDULE:
Clubhouse – Start June 19th, 2026
Buildings 7,8,9 (2475, 2464, 2470 Theresea Lane) – Start June 20th, 2026
Buildings 1,2,3 (2452, 2458, 2453 Theresea Lane) – Start Date June 22nd, 2026
Buildings 4,5,6 (2459, 2463, 2467 Theresea Lane) – Start Date June 23rd, 2026
Buildings 10,11,12 (2466, 2458, 2452 Brookwillow Loop) – Start Date June 27th, 2026
ROOFING CONSTRUCTION SCHEDULE:
Clubhouse – Start June 22nd, 2026
Buildings 7,8,9 (2462, 2468, 2475 Theresea Lane) – Start June 22nd, 2026
Buildings 1,2,3 (2451, 2452, 2456 Theresea Lane) – Start Date June 24th, 2026
Buildings 4,5,6 (2455, 2461, 2467 Theresea Lane) – Start Date June 25th, 2026
Buildings 10,11,12 (2450, 2458, 2464 Brookwillow Loop) – Start Date June 29th, 2026
Contractor hours are between 6 AM and 8 PM Monday thru Friday
ROOF REPAIR WAIVER AND CONSENT
Letter Regarding Roofing Contractor Selection
Architectural Advisory Committee – Construction Kickoff Meeting #1: March 30th, 2026
Architectural Advisory Committee – Construction Kickoff Meeting #2: April 6th, 2026

Architectural Shingles
TAMKO Titan XT Class 3 Shingles
Class 3 Impact Rated 160 MPH
Homeowners Association – CAU Insurance

Old Mechanical Wells identified in Red
New Mechanical Wells identified in Green




Colorado Energy Office
HB22-1362 – Model Low Energy and Carbon Code


ARMSTRONG 2026- Packaged Roof Top Unit
Armstrong – 3 Ton Gas/Electric
SEER 14 PRPGE 14
Recommended by Coppersmith Plumbing to Replace 2007 era Lennox Units
Townhouse Unit Owner’s Responsibility/Liability

LENNOX 2007 Packaged Roof Top Unit
Typical HVAC unit Filing 1
Lennox – 3 Ton Gas/Electric
19 Years Old
Frequent repairs and failures