Townhouse Buildings Roofing Project

Final shingle border work around mechanical wells July 16th, 2026

Punchlist Items week of July – August, 2026

HVAC / Mechanical Well Construction Schedule Start Date (Last Updated 7/8/2026 at 9:45)

Monday July 6th – Removal of units from buildings 1,2, and 3 – Completed

Tuesday July 7th – Reset of units on buildings 1,2, and 3 – Completed

Wednesday July 8th – Removal of units fromCompleted

building 4 – 2 units (2455 1/2, 2457, 2457 1/2 Theresea) – Completed

building 6 – all units – Completed

building 7 – 2 units (2473, 2473 1/2 Theresea) – Completed

building 9 – 4 units (2468, 2468 1/2, 2470, 2470 1/2 Theresea) – Completed

Thursday July 9th – Reset of all units listed aboveCompleted

Monday July 13th – 15th – Removal & Reset of remaining roof top units

building 5 – 2 units (2463 1/2, 2465 1/2 Theresesa) – Completed

building 8 – 3 units (2462 1/2, 2464, 2464 1/2 Theresea) – Completed

building 10 – 4 units (2464, 2468, 2468 1/2, 2470 Brookwillow) – Completed

building 11 – 2 units (2460 1/2, 2462 Brookwillow) – Completed

building 12 – 3 units (2452 1/2, 2454, 2456 Brookwillow) – Completed

***Note: This schedule could change due to weather or any unforeseen delays***

COPPERSMITH PLUMBING WILL BE RECONNECTING THE GAS LINES TO ALL RTUs THAT WERE A PART OF THIS PROJECT THE FIRST OR SECOND WEEK OF AUGUST, 2026.

Mechanical Wells

Preferred Filing 1 Townhouse EPDM reroofing material.

The mechanical wells have historically been prone to leaking.

Homeowners Association – CAU Insurance

HANG OUT AT THE CLUBHOUSE

During the roofing project the community clubhouse is a great place to hang out.

Stay cool, don’t have to listen to hammers and work crews walking on your roof all day.

Playgrounds and televisions for the kiddos, kitchen to prepare snacks or keep beverages cool in the refrigerator, work out or exercise.

Humpty Dumpsters – Container Locations During Reroofing.

Containers can be expected to be in location for up to 2 days.

Homeowners please inform your tenants of the temporary disruption to parking in the driveways during construction.

Overflow parking in available on: Theresea Lane Parking Area #3, Brookwillow Loop, Brookwillow Loop Parking Area #4, Abas Drive Northside (F3/4 Road)

See HOA Website : Community Parking

TRASH CONTAINER LOCATION / SCHEDULE:

Clubhouse – Start June 19th, 2026

Buildings 7,8,9 (2475, 2464, 2470 Theresea Lane) – Start June 20th, 2026

Buildings 1,2,3 (2452, 2458, 2453 Theresea Lane) – Start Date June 22nd, 2026

Buildings 4,5,6 (2459, 2463, 2467 Theresea Lane) – Start Date June 23rd, 2026

Buildings 10,11,12 (2466, 2458, 2452 Brookwillow Loop) – Start Date June 27th, 2026

ROOFING CONSTRUCTION SCHEDULE:

Clubhouse – Start June 22nd, 2026

Buildings 7,8,9 (2462, 2468, 2475 Theresea Lane) – Start June 22nd, 2026

Buildings 1,2,3 (2451, 2452, 2456 Theresea Lane) – Start Date June 24th, 2026

Buildings 4,5,6 (2455, 2461, 2467 Theresea Lane) – Start Date June 25th, 2026

Buildings 10,11,12 (2450, 2458, 2464 Brookwillow Loop) – Start Date June 29th, 2026

Contractor hours are between 6 AM and 8 PM Monday thru Friday

ROOF REPAIR WAIVER AND CONSENT

Letter Regarding Roofing Contractor Selection

Architectural Advisory Committee – Construction Kickoff Meeting #1: March 30th, 2026

Architectural Advisory Committee – Construction Kickoff Meeting #2: April 6th, 2026


Architectural Shingles

TAMKO Titan XT Class 3 Shingles

Class 3 Impact Rated 160 MPH

Homeowners Association – CAU Insurance


Old Mechanical Wells identified in Red

New Mechanical Wells identified in Green


Colorado Energy Office

HB22-1362 – Model Low Energy and Carbon Code

ARMSTRONG 2026- Packaged Roof Top Unit

Armstrong – 3 Ton Gas/Electric

SEER 14 PRPGE 14

Recommended by Coppersmith Plumbing to Replace 2007 era Lennox Units

Townhouse Unit Owner’s Responsibility/Liability


LENNOX 2007 Packaged Roof Top Unit

Typical HVAC unit Filing 1

Lennox – 3 Ton Gas/Electric

19 Years Old

Frequent repairs and failures

Townhouse Unit Owner’s Responsibility/Liability